SR 25

Widening and realigning the one road out of the county

Every County Express intercounty trip and most of the county's commute traffic use State Route 25 between Hollister and Gilroy. The improvement project widens and realigns that stretch of highway and adds a proposed frontage road, following the range of alternatives SBCOG published for public review.

Two-lane State Route 25 running between fence lines and the dry gold hills of San Benito County
State Route 25 in the two-lane rural condition the project is widening. Photo: Darmok and jalad at tanagra, View of CA 25, CC BY-SA 4.0, via Wikimedia Commons.

What changes and where

The published record

SBCOG's purpose and need statement, its range of alternatives, and its fact sheet all describe the same stretch of highway between Hollister and Gilroy. The range of alternatives is the document to read for the specific alignment options SBCOG studied, including the proposed frontage road.

Where this sits in the corridor's history

Phases on this stretch of road

  1. Complete, February 2024

    25/156 turbo roundabout

    The junction where State Route 25 meets State Route 156, at the south end of this same corridor, finished construction in February 2024 after breaking ground in May 2022.

  2. Published, October 2024

    Purpose, need, and range of alternatives

    SBCOG published the project's purpose and need statement, its fact sheet, and its range of alternatives for the Hollister-to-Gilroy stretch.

  3. Published, February 2025

    Frequently asked questions

    SBCOG published a corridor-wide FAQ answering questions raised about the range of alternatives.

This build does not state a construction start or completion date for the SR 25 mainline work beyond what SBCOG has published above. Ask SBCOG directly for the current schedule.