Construction Updates
Every City engineering project, what stage it is at, and when it is expected to finish.
Active Projects
Every project on the City's engineering list, in the City's own order, with its latest status note. The City updates this list as each one moves.
Ashworth Road Reconstruction - 19th Street to 23rd Street
Roadway improvements on Ashworth Road (from 19th Street to 23rd Street) are ongoing. Starting August 20th, contractors limited access between 20th Street and 22nd Street for storm sewer installation.
Updated 08/26/2026
Booneville Road Reconstruction – S. 60th to Raccoon River Drive
This section of Booneville Road remains closed for paving.
Updated 08/26/2026
EP True Parkway – Bridgewood Boulevard to Wendover Lane, and Grand Prairie Parkway to Bridgewood Boulevard
The contractor opened EP True Parkway from Wendover Lane to South Grand Prairie Parkway to traffic on August 17th. Crews will remain on site for final punch list items, as well as restoration and clean up.
Updated 08/18/2026
Grand Avenue Reconstruction – I35 to South 60th Street
Paving of the new lanes is complete. The contractor is currently finishing installation of the new traffic signal at the intersection of 60th Street and Grand Avenue, median construction, and backfill.
Updated 08/26/2026
Grand Avenue Sewer Abandonment - S. 33rd To Jordan Creek
The City has not posted a status note for this project yet.
Grand Avenue Widening - South Jordan Creek Pkwy to South 60th Street
The City has not posted a status note for this project yet.
Grand Prairie Parkway & EP True Parkway Intersection Improvements
The contractor has completed paving at the intersection, the medians are complete, and the traffic signals have been installed and activated. Work continues on restoration and punch list items.
Updated 08/26/2026
Mills Civic Parkway Reconstruction - S. 91st to S. Grand Prairie Parkway
The contractor has closed Mills Civic Parkway from South 91st Street to South Grand Prairie Parkway. Phase 1—which involved grading, storm sewer installation, roadway paving, erosion control, and tying into the existing pavement at South 91st Street—is now complete.
Updated 08/12/2026
Mills Civic Parkway Widening – S. 81st Street To S. 88th Street
This project is substantially complete. The contractor will remain on site to complete punch list items and restore the site.
Updated 08/26/2026
Riverview Drive & South 81st Street Extension
Mainline paving is complete and finish grading is in progress. Trail paving along Riverview Dr and S 81st St is expected to start the week of August 31st.
Updated 08/26/2026
SE Salix Drive – Veterans Parkway to SE 1st Street
The contractor has finished earthwork, site grading, water main, and storm sewer installation. They have begun subgrade and subdrain work to prepare the site for paving in September.
Updated 08/26/2026
Stonewood Pavement Repairs
Iowa Contracting is paving Stonewood Dr on August 26th. Once the new pavement has adequately cured they will begin driveways and backfill of the right-of-way.
Updated 08/26/2026
Valley Junction Alleys - Phase 10
The City has not posted a status note for this project yet.
12th & Vine Regional Stormwater Detention Facility
Grading operations are nearly complete. Installation of storm sewer structures is expected to begin in 1 to 2 weeks.
Updated 08/26/2026
16th Street & Grand Avenue Intersection Improvements
The contractor closed the intersection at 16th Street to begin pavement removal the week of July 20th. One lane of Grand Avenue remains open in each direction.
Updated 08/12/2026
2026 HMA Resurfacing Program - Phase 1
The contractor has completed paving on 13th Street (Grand Avenue to Vine Street), Prospect Ave (24th Street to 19th Street), 72nd Street, 68th Street, and Woodland Avenue, Western Hills Drive (47th Street to Valley West Drive), Aspen Drive (47th Street to 41st Street); 17th Street (Buffalo Road to Center Place); Ponderosa Drive; the intersection of 71st and Dakota; 45th Street (between Woodland and Pleasant); Wistful Vista Drive (S. 49th Street to Meadow Valley Drive); and Stonebridge Road (39th Street to Valley West Drive).
Updated 08/26/2026
2026 HMA Resurfacing Program - Phase 2
Roadway improvements are complete on Woodland Ave (22nd Street to 20th Street), Woodland Avenue (28th to 22nd Street), 24th Street (Woodland Ave to 1148 24th Street), and 18th Street (Ashworth Road to Woodland Avenue). Under single-lane closures, crews will return to finalize sidewalks, intake box outs, and restoration until all project requirements are met.
Updated 07/29/2026
2026 PCC Patching Program - Phase 1
Roadway improvements along Prairie View Drive (EP True Parkway to Aspen Drive) have begun, and this section of road is closed to through traffic. Roadway improvements along 52nd Street and Boulder Drive (Walnut Street to Knolls Road) will begin on Friday, August 28th.
Updated 08/26/2026
2026 PCC Patching Program - Phase 2
Roadway improvements along Lake Drive (Jordan Creek Parkway to Westown Parkway) have begun. This section is currently reduced to a single lane for concrete saw cutting.
Updated 08/26/2026
2026 Street Reconstruction Program - Giles Street (32nd to 28th)
The contractor has started subgrade preparation on Phase 2 to prepare the site for paving.
Updated 08/26/2026
2025 Channel Repair Program
The City has not posted a status note for this project yet.
Enter your address on the home page and the work on your street is named for you.
Why a Street Gets Worked On
Which stage a street is in decides whether it gets patched, resurfaced, or rebuilt, and how long the work takes.

Snow and Ice
Route priorities, what to expect after a storm, and the rules for parking during a snow event.

Stormwater
The Stormwater Assistance Program and what the City asks residents to keep clear of intakes.