Franklin · Merrimack County

Winnipesaukee River Basin, Franklin: Energy Audit Measures Implementation

Approved
June 29, 2022
NHDES funding
$189,100
Water system
Wastewater
Kind of work
Energy efficiency

About the project

The funds will be used to make improvements to the aeration process at the Franklin Wastewater Treatment Facility as recommended in the 2019 Energy Evaluation completed by Process Energy Services.

How it was funded

Funding for this project by program
ProgramAmount
American Rescue Plan Act$189,100
NHDES funding$189,100