Winchester · Cheshire County
Town of Winchester: Critical Flood Infrastructure
- Approved
- November 22, 2022
- NHDES funding
- $400,000
- Water system
- Flood risk
- Kind of work
- Construction
About the project
The Town of Winchester will use funds to replace the Jones Culvert, a high-risk, 70-year-old, undersized culvert. Replacement is critical to prevent the collapse of the road and significant public safety issues. This project will allow the Town to complete the construction of an improved crossing that passes the 100-year storm event and allows aquatic organism passage.
How it was funded
| Program | Amount |
|---|---|
| American Rescue Plan Act | $400,000 |
| Local funds | $28,950 |
| NHDES funding | $400,000 |
| Total project cost | $428,950 |