About the project
The Town of Seabrook will use the funding to make improvements to the wastewater treatment facility (WWTF) and the wastewater collection system. Proposed improvements may include replacement or rehabilitation components of the headworks WWTF, upgrades to pumps and their variable frequency drives (VFDs) at the facility, improvements to the belt filter press system, upgrades to the programmable logic controllers (PLCs) and Supervisory Control and Data Acquisition (SCADA) software, improvements to the Meter Vault at the WWTF and installation of radios and supporting hardware at pump stations and the WWTF.
How it was funded
| Program | Amount |
|---|---|
| American Rescue Plan Act | $528,800 |
| Clean Water State Revolving Fund | $2,115,200 |
| NHDES funding | $2,644,000 |
| Total project cost | $2,644,000 |