Exeter · Rockingham County
Town of Exeter: Clean Water Infrastructure & Planning
- Approved
- December 7, 2022
- NHDES funding
- $430,715
- Water system
- Wastewater
- Kind of work
- Construction
About the project
The town will use the grant and loan funding for final design engineering, and preparation of permits and bid documents aimed at implementing the recommendations for providing better stormwater controls and treatment outlined in the Westside Drive Sewer Planning Study, dated May 23, 2023. In addition, the town will use the grant funding for a study to evaluate modification and removal alternatives for Pickpocket Dam.
How it was funded
| Program | Amount |
|---|---|
| American Rescue Plan Act | $199,215 |
| Clean Water State Revolving Fund | $231,500 |
| NHDES funding | $430,715 |
| Total project cost | $430,715 |