Hampton · Rockingham County

Aquarion Water Company, Hampton: PFAS Remediation

Approved
July 27, 2022
NHDES funding
$1,769,509
Water system
Drinking water
Kind of work
Construction

About the project

Aquarian used the grant to assist with financing necessary water system improvements to remediate PFAS contamination in the Mill Road well field by way of activated granular carbon. The bidding process occurred in March and April of 2021; construction began June 23, 2021. The approved project scope included bidding, construction and engineering oversight for the renovation of an existing pumphouse to accommodate treatment vessels, installation of treatment and necessary pipe work to connect the affected well(s). Substantial completion was issued on December 21, 2021.

How it was funded

Funding for this project by program
ProgramAmount
American Rescue Plan Act$1,341,259
Drinking Water and Groundwater Trust Fund$428,250
NHDES funding$1,769,509
Total project cost$1,769,509