Pablo 31A Chute Replacement
River or area
Mission Valley reservoirs and canals
Pablo
Program
Status
Completed
Now
Completed spring 2025.
Confederated Salish and Kootenai Tribes
Natural Resources Department
Division of Engineering & Water Resources
Project Overview
An aging 626-foot concrete chute is set on a steep slope and is operated by FIIP conveying an estimated 50 cubic feet per second. In 2019, FIIP installed materials to reduce seepage. This project will include replacing the concrete chute with a buried 36-inch diameter steel pipe, new concrete inlet structure with debris screen and a new energy dissipation structure at the pipe outlet. Maximum flows will remain the same, however, the improvements will increase operator safety. Seepage mitigation will protect the headworks and chute structures from soil erosion around the foundation.
Design drawing
Site Plan
By year
Phases
2022 to 2023
Design
Done
Summer and fall 2024
Construction
Done
Spring 2025
Completed
Done
Before replacement
The Old Structure