Jocko Valley Canal-to-Pipeline Conversion
River or area
Jocko River
Arlee, east of US 93
Program
Status
Under way
Now
Phases 5 and 6 awarded to Knife River, to begin after the 2026 irrigation season.
Updated October 22, 2026
Confederated Salish and Kootenai Tribes
Natural Resources Department
Division of Engineering & Water Resources
Converting aging open canals to buried pipelines to improve water delivery efficiency, reduce water loss, and modernize irrigation infrastructure.
- of pressurized, buried pipe
- 17.7 miles
- in the master plan
- 6 phases
Project Overview
The Jocko Service Area of the Flathead Indian Irrigation Project has been identified as a high-priority target for rehabilitation, betterment and modernization as it relates to water delivery efficiencies. The Jocko K Canal irrigation service area will be rehabilitated with a delivery network of pressurized, buried pipe. Pressurized pipe operates by completely filling the pipe with water, allowing the pipe to pressurize by the effect of gravity. A Master Plan for the area was developed as a collaborative effort between the engineering services of Morrison-Maierle, CSKT, and FIIP staff. The conceptual design is split into six phases over the next few years that will involve 17.7 miles of pipeline. Some of the challenges in the Jocko service area include canals overgrown with vegetation, high seepage, due to the character of underlying soils, and flow control structures.
Project map
Project Phasing
For neighbors
Where and What to Expect
Construction will occur east of Highway 93 between Oliver Thomas Lane and Sodfarm Road. Please expect construction vehicles and occasional traffic interruption on the following roads:
- Oliver Thomas Lane
- Theresa Adams Lane
- McLeod Road
- Dumontier Road
- White Coyote Road
- Martz Drive
- Scotch Pine Lane
- Lost Horse Lane
- Traffic detours will help maintain access during construction.
- Local access will remain open.
- Construction zones will be clearly marked and secured for safety.
- Irrigation services will not be disrupted.
By year
Phases
2022 to 2023
Design
Done
2025 to April 2026
Phases 1 to 4 construction
Done
After the 2026 irrigation season
Phases 5 and 6 construction
Under way now