Project
Falls Creek Diversion Replacement
River or area
North Fork Jocko and the Tabor Feeder Canal
Tabor Feeder Canal
Program
Status
Scheduled to finish summer 2025
Now
Construction to be completed summer 2025.
Updated July 2025
Confederated Salish and Kootenai Tribes
Natural Resources Department
Division of Engineering & Water Resources
Project Overview
Falls Creek is a natural and ungauged stream along the Mission Mountain divide and is a major tributary to the North Fork of the Jocko River. The diversion is a reinforced concrete irrigation structure collecting and conveying surface water flows at its intersection within a concrete lined portion of the Tabor Feeder Canal. The diversion, made of a debris screen/rack, rectangular flume, check structure, and radial gates, is highly degraded and needs full replacement. As part of a Modernization Plan, recommendations include a new trash rack, radial gates, flap gates, and flow measurement structures. Debris management is expected to be a significant design parameter for the diversion structure. A modern system will include minimal maintenance requirements, improved operational flexibility, and long-term durability.
By year
Phases
2023
Design
Done
2024
Bid
Done
Fall 2024 to summer 2025
Construction
Done
Before replacement
The Old Structure