Council Agenda item 9C

Change Order #1 for Mt. Baldhead Restroom Replacement

City Council, Tuesday, May 27, 2025

Download these 2 pages, 723 KB Whole packet, 188 pages, 16.0 MB

Page 7

Page 7 of the packet; its text follows
Text of page 7

City Council Agenda Item Report FROM:

Ryan Cummins, City Manager

MEETING DATE:

May 27, 2025

SUBJECT:

Change Order #1 for Mt. Baldhead Restroom Replacement

DESCRIPTION: During approval of the Mt. Baldhead restroom replacement bid, City Council advised they would like the work to be completed in the fall after the Mt. Baldhead Challenge. Fleis & Vandenbrink provided the attached change order. The change order changes the contract times to reflect a mobilization date on or after September 8, 2025 and substantial completion by December 5, 2025. BUDGET ACTION: None required. LEGAL REVIEW: N/A at this time. SAMPLE MOTION: Motion to approve change order #1 for the Mt. Baldhead restroom replacement.

Page 8

Page 8 of the packet; its text follows
Text of page 8

CHANGE ORDER NO.: 1 Owner: City of Saugatuck Owner’s Project No.: N/A Engineer: Fleis & VandenBrink Engineer’s Project No.: 860451 Contractor: Midwest Construction Group Contractor’s Project No.: N/A Project: Mt. Baldhead Restroom Replacement Contract Name: N/A Date Issued: May 21, 2025 Effective Date of Change Order: May 21, 2025 The Contract is modified as follows upon execution of this Change Order: Description: The Contract Times are hereby changed to reflect a mobilization date on or after September 8, 2025. Attachments: None Change in Contract Price

Change in Contract Times

Original Contract Price: $

Original Contract Times:

298,000.00

Increase (Decrease) from previously approved Change Orders No. N/A to No. N/A: $

0.00

Contract Price prior to this Change Order: $

298,000.00

Ready for final payment:

August 29, 2025

Increase (Decrease) from previously approved Change Orders No. N/A to No. N/A: Substantial Completion:

N/A

Ready for final payment:

N/A

Substantial Completion:

August 15, 2025

Ready for final payment:

August 29, 2025

Increase (Decrease) this Change Order:

0.00

Contract Price incorporating this Change Order:

August 15, 2025

Contract Times prior to this Change Order:

Increase (Decrease) this Change Order: $

Substantial Completion:

298,000.00

Substantial Completion:

112 days

Ready for final payment:

112 days

Contract Times with all approved Change Orders: Substantial Completion:

December 5, 2025

Ready for final payment:

December 19, 2025

Recommended by Engineer (if required) By: Title: Date:

Authorized by Contractor

Jon Moxey, PE, Project Manager Approved by Funding Agency (if applicable)

Authorized by Owner By: Title: Date:

860451

N/A

01 26 00 - 1

CONTRACT MODIFICATION PROCEDURES