Commercial Plans Review - Standard Operating Procedure
Text
Recovered from a scanned original, so it can be searched and read aloud.
Length
27,752 characters
Original
CITY OF EAST RIDGE COMMERCIAL PLANS REVIEW STANDARD OPERATING PROCEDURE PLANS REVIEW STANDARD OPERATING PROCEDURES (S.0.P.) The purpose of this document is to inform all concerned of the process involved in plans review for development projects within the City of East Ridge other than one and two family residential. Pre-Submittal Meeting In an effort to improve the efficiency and responsiveness of the process, a system for pre- submittal meetings has been initiated. In attendance are the staff members responsible for review of the site plans (civil drawings) from the appropriate agencies within the city, (SEE attachments H & I) At this time architects, developers, contractors, engineers and/or owners are afforded the opportunity to meet with the reviewers regarding their projects, prior to formally submitting their plans for review. At this meeting the applicant is asked to make a brief presentation of their project and then the staff reviewers comment and state site specific requirements to be addressed for the project within the scope of their individual responsibilities. In attendance at the preOsubmittal meetings are reviewers from Storm Water, Engineering, Traffic Engineering, Waste Resources, and Building Inspection. A site survey worksheet (Attachment A) is given to the applicant in advance, to assist in providing the review staff the information necessary to make the pre-submittal meeting as productive as possible. The applicant is encouraged to ask questions and to contact any member of the review staff for additional assistance. Also, they may schedule another pre-submittal meeting as the project evolves to assure that all requirements for submittal of a complete set of plans have been met. Plans Submittal Requirements 1. Plans are to be submitted to Hast Ridge Building Inspection at 1517 Tombras Avenue, between 8:00 AM and 4:00 PM (Eastern Standard Time), Monday through Friday. 2. Full plan sets include all building plans (architectural, structural, mechanical, gas, electrical, plumbing) and site plans (civil drawings). SITE PLANS MUST PROVIDE ALL REQUIRED INFORMATION TO BE ELIGIBLE FOR REVIEW, Plans must be clear and legible and drawn to scale. They must also be signed and sealed, as required by state law. Failure to submit a full set of plans will delay the review process. See Attachment B for contact information. 3. Three full sets and three civil sets of plans are required for review 4. Site plans require specific information as prescribed in Attachment C. Attachment C must be filled out, signed by the person that prepared the plan, and submitted with the plans. Site plans will be submitted on size “D” (24 x 36) bond paper. 5. Additionally, a completed Construction Activity Permit, (Attachment D), a completed Building Permit with a check for plans review (Attachment D-1), and a completed Plans Review Contact Form (Attachment E) are required for submittal. 6. Additionally, a completed Construction Activity Permit (see Attachment D for example) and a completed Pians Review Contact Form (Attachment E) are required for submittal. 7. Sprinkler plans and fire alarm drawings must be submitted to the East Ridge Building Department at 1517 Tombras Ave. and the State of Tennessee Fire Marshall’s office when required. 8. Complete sign plans must be submitted directly to the Chief Building Official of East Ridge at 1517 Tombras Avenue, East Ridge TN 37412 for review. 9, fall required information is provided which meets City standards and policy, the objective is to complete the review process from log-in to issuance of the Construction Activity Permit within ten working days. Pending State of Tennessee Fire Marshall’s review of Construction Documents, and TDEC’s NPDES permits application, etc... 10, See Attachment F for plans review routing, Plans Review Process If during the review, a reviewer has a need for further information to complete or approve a set of plans, the reviewer will use the Plans Review Contact Form (Attachment E) to notify all parties concerned of the need for additional information. Prompt response to the request for additional information will assist in the completion of the review process in a timely manner. To prevent a backlog of plans whose review has extended beyond the expected review period, the Plans Review Contact Form will be used to contact all concerned parties that the review process has been suspended and that the plans, as submitted, may be retrieved at the plans review office. A written notice to this effect will be sent to all parties concerned. (see Attachment J) Ié, after 10 working days, the plans are not retrieved, it will be assumed that the plans, as submitted, have no value to the parties involved and the plans will be discarded. ATTACHMENT “A” Site Survey Worksheet Your ability to provide the following information at the Pre-submittal Meeting will substantially increase the productivity of the meeting. 1 Location of Project a, Street Address #. Street Name, b. Nearest Cross Streets, 2 ce. Tax Map # 7 By Zoning for property involved and for adjacent properties. a Property b, » s Adjacent Properties Are there “special zoning requirements, design criteria, or conditions” on the property? a. Ifyes; what are they; {attach a copy of zoning case, design criteria, or Board of Appeals case) Locations of Utilities (On property or on adjacent streets) a, Sewer i. Cily Mains ii. Service Tees, Wyes, stubs ili, Manholes b. Power c, Water i. Lines ii. Fire service and hydrants d. Catch Basins e Gas 5. Location of Utility Easements (Sewer, Gas, Water, Power Lines) a. Do they exist? Yes No b. Location on Property G. Drainage Hasements a. Do they exist? Yes No b. Location on Properly 7 Location af Overhead Power Lines, (high voltage, telephone, cable) a. Do they cxist? Yes No b. Type c, Location on or adjacent to property i, On Street: : ii. Across Property Yes, No 8. Publicly owned Trees adjacent to Project a. Existence Yes No b. Location in reference to property, Show Existing Parking & Driveways 10, What is the square footage of: a. Existing Building/s b. Expansion / New Building/s c. Warehouse / Storage space d. Retail Space ATTACHMENT “B” CITY/COUNTY DEPARTMENT PHONE NUMBERS Building and Fire Inspection (Plans Review) 423-867-7711 1517 Tombras Avenue East Ridge, TN 37412 East Ridge Fire Department 423-867-7100 4214 Ringgold Road East Ridge, TN 37412 Hamilton County Health Department 423-209-8110 921 Hast 3 Street Chattanooga, TN 37402 Environmental Health (Groundwater/Flood) 423-209-7782, 1250 Market Street, Suite 1030 Chattanooga, TN 37402 Regional Planning Commission (Zoning) 423-668-2287 1250 Market Street, Suite 2000 Chattanooga, TN 37402 Hamilton County WWTA 423-209-7842, 1250 Market Street Chattanooga, TN 37402 Hamilton County Water Quality 423-209-7853 1250 Market Street Chattanooga, TN 37402 Traffic Engineering ~ Mike Ailey 423-892-3169 1517 Tombras Avenue Bast Ridge, TN 37412 Air Pollution Control Board 423-643-5970 6125 Preservation Drive Chattanooga, TN 37416 Planning & Design Studio 423-668-2262 1250 Market Street, Suite 3010 Chattanooga, TN 37402 ATTACHMENT “B” continued UTILITIES PHONE NUMBERS Electric EPB 423-648-1372 10 West ML King Blvd. Chattanooga, TN 37411 Gas 1-800-427-5463 Atlanta Gas/Light Company Telephone EPB 423-648-1372 AT&T 1-800-288-2020 Water Tennessee American Water Company New Development of Construction 423-157-1527 Hixson Utility Eastside Utility Cable/Internet 423-855-4300 Comcast Cable EPB 423-648-1372 ATTACHMENT “Cc” Storm Water & Erosion Control Checklist Provide Note “Disturbed Acreage= Provide NOI, NOC, or NPDES permit if Disturbed Acreage is > 1.0 acre, Provide Notes “Preconstruction Impervious Acreage = : “Postconstruction Impervious Acreage = If constiuction results in an increase in impervious acreage, provide a Hydrology Report from a TN P.E. (2 copies). The Hydrology reports should provide information as follows; 1, Model the 2,5,10,25, and 100-year storm events Pre and Post development, 2. Ifa runoff increase is calculated > 0.1 CFS for the 2 through 25 yr. Storm events, then provide detention. 3. Size pond to detain the 25 yr. Storm event 4, Provide stage release for the 2 through 25 year storm events, 5. Provide summary table on Page One clearly stating all assumptions and design conclusions. 6, Demonstrate and provide certification that pond outfall structure or piping operates under inlet control for the 2 through 25 yr, Storm event if inlet control is assumed. Capture and filter the first flush (first % inch sile rainfall). Label all site storm water outfalls and provide energy dissipation (rip-rap, etc.) Provide oit skimmers before storm flow reaches the pond or public storm sewer if drainage is from paved parking. Provide Note “Number of Oi! Skimmers = ” Provide Pond dimensions and volume. An inventory of constructed drainage and Engineers Certification will be required prior to the release of the Certificate of Occupancy, Provide a detail drawing of the staged release outlet structure Show pond outfall structures and pipes with pipe sizes and materials. Provide a paved emergency spillway for pond. Provide Note “Owners Representative for Erosion Control Maintenance Name and Phone if.” Provide Note “Site erosion controls sali be checked and if necessary, repaired weekly and within 24 hours after each rainfall > 4”. In the event of continuous rainfall, cresion controls shall be checked daily. Provide and label a concrete track wash out area Provide Note “ All areas to remain bare greater than 15 days must be stabilized.’ Provide 100 year flood elevation for pre and post development Grading, Site and Erosion Control Plan. Provide Note “Projeet is above the 100 year flood elevation as determined by FEMA flood map Dated February 3", 2016”. Ifa 100-yr flood elevation has not been established, then please state. Note: This may be placed on Grading and Site Plan. Picase show existing floodways as shaded area. Note: ‘This may be placed on the grading plan. Provide a construction activity permit (complete with the signature of owner or general contvactor)with plans submital. Provide a completed, signed and stamped Storm Water Calculation Summary Sheet with plans submittal. STORMWATER CALCULATION SUMMARY SHEET PROJECT NAME DATE ADDRESS HYDROLOGIC METHOD USED : OTrationat Cl mouited Rational ~— (Check One) Uses TOTAL AREA (Acreage) PRE-CONSTRUCTION GONDITIONS Pervious Area, Ac C or CN Factor Impervious Area, Ac C or CN Factor Time of Concentration Method for To POST-CONSTRUCTION CONDITIONS Pervious Area, Ac C or CN Factor Impervious Area, Ac C or CN Factor Time of Concentration Method for Tc RUNOFF RESULTS Storm Event Pre-Development Post-Development } Routed (detention) Peak Flowrate, cfs Peak Flowrate, cfs Flowrate, cfs 2 year 5 year 10 year 25 year 100 year DETENTION VOLUME REQUIRED, cubic feet MULTI-STAGE OUTLET REQUIRED lves (no (check) Your Seal Here FIRST FLUSH VOLUME, cubic feet WATER QUALITY TREATMENT METHOD PROFESSIONAL ENGINEER CERTIFICATION NAME SIGNATURE TN PE LICENSE ATTACHMENT “C” Continued Three (3) Full sets of plans attached OM Three (3) Separate Civil Sets Completed Building Permit with Plans Review Fee Completed Construction Activity Permit || KK Review Contact Form with Complete Address & Fax Number ww ( 1. Title of Project w/Address & Parcel Number x 2. Date of Preparation and All Revisions x 3. Legend on each page x 4. Graphic scale (not less than 1” = 40’) x 5. Location map (Recorded Plat or Boundary Survey Stamped and Signed by Licensed Surveyor). 6. Site Plan with adjacent property shown, Buildings Correctly located and labeled and compass orientation of the parcel shown. Ki oe 7. Zoning of property and surrounding properties x 8. Bldg location with dimensions, sq ft. F.F.E. and lot dimensions Ki 9, Dimensions from bldgs to property lines & easements, x 10. Location of all casements and utilities, public & private w/dimensions x 11, Show flood elevations (100-yr flood) and floodways. if appl. 12. Show walks, truck loading arcas and driveways. x 13. Corrective plat. If appl. 14. Curb, gutter, sidewalk plan if appl. 15. Parking layout with entrances, exits and parking ratios x 16. Building Code Synopsis on first page x 17. Location and case number of all granted variances if appl. 18. Dumpster Area with Enclosure Details if appl. 19. Parking Plan showing required spaces; label Handicap, Regular and Van x 20. Construction entrances and exits x 21. Concrete wash-out area x 22, 25 Street names x 23. eee ye to streets and all seers x 1. Storm water plan / erosion control / grading plan w/City notes if appl. 2. Hydrology Report (increase of imperviousness) x 2 if appl. 3. Notice of Intent (NOI) {1 + acre}. NOC required before permit will be issued. if appl. 4. Detention/Retention pond or wetland volume and dimensions if appl. 5. Existing and planned topographic survey if appl. 6. Existing and proposed contours (5’ intervals or less) if appl. 7. Site drainage if appl. 8. New & existing storm drain structures & detention facilities & tie-in City system if appl. 9, Plan & profile view for all City sewers to be constructed or modified w/all dimensions & utility paaee Seas cuts and ae if appl. 1. Interior partition(s) with dimensions a. Label all rooms and spaces as to use b. Label all rated walls & partitions — Ext. & Int. 2, Show all openings in int. & ext. walls ed 3. Show openings in floor/ceiling assemblies with dimensions 4, Door, Window, finish schedule 5. Show plan view of footing layout 6. Show sectional of oe Pe 1. Roof Plan x 2. Roof Gs Plan x 1, Complete elevation drawings x ATTACHMENT “C” Continued PON DRS SS | 1. Vertical Wall Section Exterior x 2. Vertical Wall Section Interior x 3. Sill section x 4. Beam details x : Cornice section x . Stairway section if appl. 1, Electrical drawings include riser diagram if appl. 2. Mechanical Drawings include vents if appl. 3. Plumbing include riser diagram and/or gas piping drawings if appl. ATL FOR CO} 1. Plan view dimension restrooms x 2. Show required turning radius x 3. Elevation view with dimensions x NOTES: 1. Check all boxes that apply. 2, All applicable items must be checked prior to submittal. 3, X=A plan required item 4. The Civil set of plans shall consist of Separate 24” x 36” (D size) sheets for each plan above. 5. Failure to submit plansin the required format will resultin non-review by the city and will delay permitting. I hereby certify that the above information is present and accurately represented on the plans submitted to the City of East Ridge on this day » 20 By: (Signature) (Print Name) Title: City of East Ridge Division of Building/Codes . Kenny Custer . 1517 Tombras Avenue, East Ridge, Tennessee 37412 Chief Building and Fire Office: (423) 867-7711 Fax: (423) 867-7340 Code Official kcuster@eastridgetn.go' BUILDING PERMIt APPLICATION NOTICE: Separate permits are required for electrical, plumbing, heating, ventilating, and/or air conditioning work, Permits become null and void if work or construction authorized does not commence within six (6) months, or if construction is abandoned for a period of six (6) months at any time after work is commenced. *#17 IS THE RESPONSIBILITY OF ALL APPLICANTS TO OBTAIN INFORMATION FROM ‘THE AIR POLLUTION CONTROL BUREAU AS TO WHETHER A PERMIT IS REQUIRED FOR EACH PROJECT.** Applicant Name/ Organization. Property Information: Property Address: Owner — Name/ Address/ Phone Existing Structures Zoning Flood Zone Tax Parcel # Project Information: Contractor Name & Address: Contractor’s License No, Expiration Date Architect/Engineer Name & Phone No. New Construction 0 Addition to Existing Structure O Repair/Remodel 0 Move O Demolish 0 Brietly Describe Project Construction Value $ Plans/Drawings Submitted 0 ‘To Be Completed by Building Inspector or Permit Clerk Type of Construction No. of Units Max. Occ. Load Sewer/Septic Size of Building Use Zone Fire Sprinklers Y/N Other Fire Zone Division No. Dwelling Units Thereby certify that I have read and examined this application and know the same to be true and correct all provisions of laws and ordinances governing this type of work will be complied with whether specified herein or not. The granting of a permit does not presume to give authority to violate or cancel the provisions of any other state or local law regulation construction or the performance of construction, Signature of Applicant; Date of Application: TO ALL CONTRACTORS AND HOMEOWNERS BUILDING INSPECTIONS FOOTING — when it is dug, before concrete is poured. (rebar must be two continuous 4” steel rods minimum, Metal grade pins & bulk heads must be in place or a soil bearing test will be required.) BASEMENT SLAB — before concrete is poured. ROUGH IN ON FRAMING-— before any insulation or sheetrock is installed. INSULATION INSPECTION FINAL ON STRUCTURE — when all structural items have been Division of Building Inspections & Codes Enforcement completed. Chief Building Official — Michael Howell COMBINED~ a rough-in and final inspection can be done at the same time providing that no part of the structure has been Phone Number: (423) 867-7711 concealed, covered, or enclosed in a manner that will interfere with a thorough inspection. Office Hours: PLUMBING INSPECTIONS Monday — Friday 8:00 a.m. — 5:00 p.m. PLUMBING IN SLAB -— before gravel or concrete in poured. (after hours, you may leave a message on the ROUGH IN ON PLUMBING- with a water test, before answering machine.) insulation or sheetrock. FINAL — when all fixtures have been set. CODES & EDITIONS: COMBINED -— a rough-in and final inspection can be done at the same time providing that no part of the plumbing has been International Building Code -2018 concealed, covered, or enclosed in a manner that will interfere with International Plumbing Code -2018 a thorough inspection. International Mechanical Code -2018 ELECTRICAL INSPECTIONS International Fuel Gas Code -2018 International Fire Code -2018 TEMPORARY POLE -— (when applicable.) Inter. Property Maintenance Code -2018 ELECTRICAL MISCELLANEOUS — slab, conduit, ceiling, National Electric Code -2017 septic pump, heat pump, service and/or panel change. International Energy Conservation Code -2018 ROUGH IN ON ELECTRICAL WIRING — before insulation ICC A117.1 Handicap Code -2017 and sheetrock have been installed. Life Safety Code -2018 FINAL ON ELECTRICAL — when all fixtures and receptacles have been set, panel and service are completed. COMBINED ~—a rough-in and final inspection can be done at the INSPECTIONS same time providing that no part of the electrical wiring has been concealed, covered, or enclosed in a manner that will interfere with All inspections must be called into this office one a thorough inspection. day in advance before 3:00 p.m. All permits must be GAS PIPING AND VENTING INSPECTIONS Obtained prior to inspections. ROUGH IN ON GAS -— before insulation and sheetrock have Homeowners requesting to install wiring, plumbing, been installed. Pressure test is required and must hold 10 Ibs. for mechanical, or gas piping must contact this office for 15 minutes. Instructions. FINAL ON GAS -— when all appliances have been installed. MECHANICAL INSPECTIONS To insure your inspection will be done as requested: Please have the following information to give the attendant. ROUGH IN — before sheetrock is installed. The roof, framing, 1) TYPE OF INSPECTION NEEDED draftstopping, fireblocking and bracing are in place, all ducting, specify type(framing, electrical, plumbing, gas, venting, piping and other concealed components are mechanical) and phase (rough-in, final, etc.) complete. 2) ADDRESS OR SUBDIVISION AND LOT NUMBER FINAL — when all items authorized by the permit have been 3) NAME BUILDING PERMIT IS RECORDED UNDER installed and all portions which are to be covered or 4) YOUR NAME OR COMPANY NAME concealed are so concealed. NOTE: BEFORE A STICKER FOR ELECTRICAL SERVICE WILL BE ISSUED, ALL FINALS MUST BE COMPLETED AND APPROVED. ATTACHMENT “Ek” Plans review contact form Used by reviewers during plans review process to gain further information or to notify all parties concerned of permit issuance OR suspension of review. PROJECT NAME: PROJECT ADDRESS: PRIMARY CONTACT: ADDRESS PHONE NO. FAX NO. E-MAIL ADDRESS; PROPERTY OWNER: ADDRESS: PHONE NO. FAX NO. E-MAIL ADDRESS; ARCHITECT: ADDRESS: PHONE NO. FAX NO, E-MAIL ADDRESS: ENGINEER: ADDRESS: PHONE NO. FAX NO. E-MAIL ADDRESS; CONTRACTOR: ADDRESS: PHONE NO, FAX NO. E-MAIL ADDRESS; ATTACHMENT “¥” PLANS REVIEW ROUTING PLANS SUBMITTAL REQUIREMENTS (Pre-Submittal Meeting) y PLANS SUBMITTED AND LOGGED IN \ TECHNICAL SITE REVIEW (See Attachment G) SITE REVIEW (Civil Drawings) (See Attachment H) Engineering Traffic engineering Sanitary/Combined Sewer e@eee Storm Water Management CONSTRUCTION ACTIVITY PERMIT MAY BE ISSUED AT THIS TIME BUILDING REVIEW (See Attachment 1) Architectural Structural Fire/Life Safety eens Mechanical Gas Electrical Plumbing PLANS APPROVED BUILDING PERMIT ISSUED CONSTRUCTION & INSPECTION Y CERTIFICATE OF OCCUPANCY APPENDIX F COVER SHEET FOR PLANS SUBMISSIONS PROJECT NAME: PROJECT ADDRESS: PROJECT DESCRIPTION (Scope of Work): FIRE DISTRICT: PROJECT CONTACT PERSON: (Registered Architect or Professional Engineer in Responsible Charge) TERRI RAISE RII OT TR IHR ea ERR ARCHITECTS/ENGINEERS/LANDSCAPE ARCHITECTS: List all names and pertinent information for each registrant (architect, engineers, and landscape architect) involved in the project. Include each engincering discipline represented in the project (civil, electrical, mechanical, plumbing, stractural), Name: Company Name: Phone (including area code): (ofe.) (fax) E-Mail Address (if applicable) Tennessee License Number: Design Codes/Edition IBC NFPA, Handicapped Code Edition Used NCHC______— CABO/ANSI. Type of Construction IBC NFPA Occupancy Group(s) IBC NFPA, Number of Stories (excluding basement unless educational or assembly occupancy) Height of Building from Average Grade Building Area Per Story, Existing Proposed Occupant Load Per Floor IBC. NFPA, Required Exit Width Per Floor IBC. NFPA. Number of Parking Spaces Required Proposed. Handicapped. Van Fire Protection hourly ratings for all structural components and separation of hazards components required by the applicable building code., Edition of the IBC ____ Columns _____ Beams _____Walls ____Floot/Ceiling __ RooffCeiling _____ Roof Covering ___ Corridors ____Shaft/Enclosures ____ Stair Enclosure _____ Tenant Separations ___ Occupancy Separations Sprinkler System Type Standpipe System APPENDIX F Continued Fire/Smoke Alarm System: Abbreviations Used and Meaning: WATER SUPPLY DATA (FROM NEAREST HYDRANT TO SITE) Provide the following flow test data on the plans for hydrant(s) used to meet the 500 feet for less hose lay requirement in accordance with the local authority having jurisdiction. [State Fire Marshal’s Office Policy based on NFPA 24 4.2.1 ]. Show flow test data next to the hydrant tested. Flow test must have been conducted within the last six months from start of design process. a Static pressure psi Residual pressure psi (20 psi minimum) Flow gpm (500 gpm minimum) Tennessee Department of Environment and Conservation Rules and Regulations 1200-5-1-17 paragraph 18, Party responsible for taking test (name and address). Date test taken:__ Time test taken: _____am/pm Elevation of test hydrant: General Notes: Identify use of rooms and spaces. Show area increase calculations per IBC Show wall ratings on structural, mechanical, plumbing, electrical, and fire protection drawings, Provide design live load values on plans for wind, snow, roof, floor, stairs, guard and hand railings, seismic IBC, Identify any exceptions/appeals/equivalencies and authority granting approval. Note: This plans cover sheet was developed during discussions with the State Fire Marshal’s Office and local Codes Enforcement Officials and should be used as a guideline when submitting plans to he designated reviewing authority. ATTACHMENT “G” SITE REVIEW Plans ate checked for the following site requirements: Location Map Street Name and Address Copy of Current Tax Map Name & Address of Owner/Developer Engineer/Preparer & Contact w/Phone Number Title of Project w/Address & Parcel Number Date of Preparation and all Revisions Legend Graphic Scale (Not less than 1” = 40’) Labeled Buildings Correctly Located Compass Orientation of Lot Property Zoning Zoning of Adjoining Properties Building Dimensions w/sq. ft. Boundary Lines w/Lot Dimensions Location & Size of all Utilities including Storm and Sanitary Sewers Property Relationships to Streets and All Rights-of-Way 100 Year Flood Elevation Location & Size of all Easements Setback Dimensions ATTACHMENT “H” Site Review ENGINEERING 423-867-711 Reviews plans for requirements regarding streets, curbs, putters, sidewalls and subdivisions and re-platting of properties. TRAFFIC ENGINEERING 423-892-4837 423-867-7711 Reviews plans for impacts to local traffic, access to the site, capacity required for parking lots, and requirements for handicap parking in compliance with city codes and zoning ordinances. SANITARY/COMBINED SEWER 423-209-7842 Reviews plans for impact on and use of the city’s sewer system. STORM WATER MANAGEMENT 423-867-7711 HAMILTON COUNTY WATER QUALITY 423-209-7853 Reviews plans for compliance with storm water ordinance and for compliance with erosion control measures. ATTACHMENT “1” Building Review Contact: 423-867-7711 Plan requirements are available in the Building Inspection Department 1517 Tombras Avenue The Code Synopsis shall be in compliance with Appendix F of the Tennessee Architectural and Engineering Handbook (at back of this booklet), « ARCHITECTURAL Review to insure compliance with International Building Code, Accessibility Code (physically disabled), and ICC Energy Code, Please include Life Safety Plan. « STRUCTURAL Review to insure compliance with structural load requirements per occupancy, snow, wind, and seismic loading. « FIRE/LIFE SAFETY Review to insure compliance with Life Safety Code, and International Fire Code. « MECHANICAL Review to insure compliance with International Mechanical Code. e ELECTRICAL Review for compliance with the National Electrical Code. * PLUMBING Review for compliance with the International Plumbing Code. « SIGN Review for compliance with local sign ordinance. ATTACHMENT “J” NOTICE OF PLANS REVIEW SUSPENSION Letter of Notification Date: BY CERTIFIED MAIL Return Receipt # Ta: From: The Plans Review Committee Re: Site Development Plan for: ; Tax Map Number We have reviewed the plan submitted and the following deficiencies require your action: Incomplete or missing Sanitary Sewer Plan, 423-209-7842 Comment: Incomplete or missing Storm Water Plan. 423-867-7711 Comment: 423-209-7853 Incomplete or missing Parking Plan. 423-867-7711 Comment: Incomplete or missing Street Improvement Plan. 423-892-4837 Comment: Incomplete or missing Building Plan. 423-867-7711 Comment: You were last contacted on by requesting attachments or revised plans reflecting the deficiencies noted above. To date we have not received the requested attachments or plans. You must submit the plans within ten (10) days of receipt of this letter to retain your plans in the active review process if the project has been indefinitely delayed or canceled, please notify our office at 423-867-7711 with the details and the plan will be removed from the review system. Please note that a pre-submittal review opportunity is available to anyone interested. We offer this service with the goal of speeding the plans review/permitting process. We look forward to assisting you with the completion of your project. Sincerely, The Plans Review Committee