Wastewater Treatment Plant Permit
What the Town Manager has told Mayor and Town Council about the wastewater treatment plant permit, report by report, since April 2025.
18 reports, April 2025 to September 2026
2026
-
Wastewater Treatment Plant Permitting Renewal
As a reminder, Chilhowie’s current permit expired in May. I received the town’s draft permit reissuance in July. The town has published the required public notices and the 30-day public comment period has passed. I have received word that our final permit within the next few weeks.
I once again would like to commend the town’s outstanding staff, as well as our partners at Hurt & Proffitt for undertaking this re-permitting process as this is the first time doing so since the town’s transition away from land application of biosolids and also the first since the increased scrutiny on localities related to forever chemicals (PFAS/PFOS).
-
Wastewater Treatment Plant Permitting Renewal
As a reminder, Chilhowie’s current permit expired in May. I received the town’s draft permit reissuance last month. The town has published the required public notices and is now in the 30-day public comment period. Once that timeframe is passed, I expect to receive our renewed permit.
I once again would like to commend the town’s outstanding staff, as well as our partners at Hurt & Proffitt for undertaking this re-permitting process as this is the first time doing so since the town’s transition away from land application of biosolids and also the first since the increased scrutiny on localities related to forever chemicals (PFAS/PFOS).
-
Wastewater Treatment Plant Permitting Renewal
As a reminder, Chilhowie’s current permit expired in May. I received the town’s draft permit reissuance late last week. The town is required to publish public notice, which I have attached to this report, for two consecutive weeks. After that, I will report this to DEQ and the final permit should be issued shortly thereafter.
I once again would like to commend the town’s outstanding staff, as well as our partners at Hurt & Proffitt for undertaking this re-permitting process as this is the first time doing so since the town’s transition away from land application of biosolids and also the first since the increased scrutiny on localities related to forever chemicals (PFAS/PFOS).
-
Wastewater Treatment Plant Permitting Renewal
As a reminder, Chilhowie’s current permit expired last month. As of now, the town has not received our new permit. However, the town staff has completed all necessary requirements and submitted to the Virginia Department of Environmental Quality (DEQ), which has acknowledged receipt of our submissions and has notified us that they are working as quickly as possible to complete their review. Our staff have had recent discussions with DEQ and we expect to receive our new permit any day.
I once again would like to commend the town’s outstanding staff, as well as our partners at Hurt & Proffitt for undertaking this re-permitting process as this is the first time doing so since the town’s transition away from land application of biosolids and also the first since the increased scrutiny on localities related to forever chemicals (PFAS/PFOS).
-
Wastewater Treatment Plant Permitting Renewal
As a reminder, Chilhowie’s current permit expires this month. As of now, the town has not received our new permit. However, the town staff has completed all necessary requirements and submitted to the Virginia Department of Environmental Quality (DEQ), which has acknowledged receipt of our submissions and has notified us that they are working as quickly as possible to complete their review. Our staff have had recent discussions with DEQ and we expect to receive our new permit any day.
I once again would like to commend the town’s outstanding staff, as well as our partners at Hurt & Proffitt for undertaking this re-permitting process as this is the first time doing so since the town’s transition away from land application of biosolids and also the first since the increased scrutiny on localities related to forever chemicals (PFAS/PFOS).
-
Wastewater Treatment Plant Permitting Renewal
The town continues to work with Hurt & Proffitt and the Virginia Department of Environmental Quality (DEQ) to renew our operating permit under the Virginia Pollutant Discharge Elimination System (VPDES). This renewal is required every five years, and this is the first renewal since the town moved away from land application of biosolids and also the first since monitoring for PFAS is required.
As a reminder, Chilhowie’s current permit expires in May 2026. As of now, the town has not received our new permit. However, the town staff has completed all necessary requirements and submitted to DEQ, which has acknowledged receipt of our submissions and has notified us that they are working as quickly as possible to complete their review.
-
Wastewater Treatment Plant Permitting Renewal
The town continues to work with Hurt & Proffitt and the Virginia Department of Environmental Quality to renew our operating permit under the Virginia Pollutant Discharge Elimination System (VPDES). This renewal is required every five years, and this is the first renewal since the town moved away from land application of biosolids and also the first since monitoring for PFAS is required.
As a reminder, Chilhowie’s current permit expires in May 2026. As of now, I see no reason that we won’t make that deadline.
-
Wastewater Treatment Plant Permitting Renewal
The town continues to work with Hurt & Proffitt and the Virginia Department of Environmental Quality to renew our operating permit under the Virginia Pollutant Discharge Elimination System (VPDES). This renewal is required every five years, and this is the first renewal since the town moved away from land application of biosolids and also the first since monitoring for PFAS is required.
As a reminder, Chilhowie’s current permit expires in May 2026. As of now, I see no reason that we won’t make that deadline.
-
Wastewater Treatment Plant Permitting Renewal
The town continues to work with Hurt & Proffitt and the Virginia Department of Environmental Quality to renew our operating permit under the Virginia Pollutant Discharge Elimination System (VPDES). This renewal is required every five years, and this is the first renewal since the town moved away from land application of biosolids and also the first since monitoring for PFAS is required.
As a reminder, Chilhowie’s current permit expires in May 2026. As of now, I see no reason that we won’t make that deadline.
2025
-
Wastewater Treatment Plant Permitting Renewal
The town continues to work with Hurt & Proffitt and the Virginia Department of Environmental Quality to renew our operating permit under the Virginia Pollutant Discharge Elimination System (VPDES). This renewal is required every five years and this is the first renewal since the town moved away from land application of biosolids and also the first since monitoring for PFAS is required.
As a reminder, Chilhowie’s current permit expires in May 2026. As of now, I see no reason that we won’t make that deadline.
-
Wastewater Treatment Plant Permitting Renewal
The town is currently working with Hurt & Proffitt and the Virginia Department of Environmental Quality to renew our operating permit under the Virginia Pollutant Discharge Elimination System (VPDES). This renewal is required every five years and this is the first renewal since the town moved away from land application of biosolids and also the first since monitoring for PFAS is required.
Last month I reported to you that I had signed the application packet and that it had been submitted to DEQ. Since that time, DEQ staff have requested two minor amendments to the packet. Staff has worked with Hurt & Proffitt and the revised packet has been resubmitted.
As a reminder, Chilhowie’s current permit expires in May 2026. As of now, I see no reason that we won’t make that deadline.
-
Wastewater Treatment Plant Permitting Renewal
The town is currently working with Hurt & Proffitt and the Virginia Department of Environmental Quality to renew our operating permit under the Virginia Pollutant Discharge Elimination System (VPDES). This renewal is required every five years and this is the first renewal since the town moved away from land application of biosolids and also the first since monitoring for PFAS is required.
Last month I reported to you that I had signed the application packet and that it had been submitted to DEQ. Since that time, DEQ staff have requested two minor amendments to the packet. Staff has worked with Hurt & Proffitt and the revised packet has been resubmitted.
-
Wastewater Treatment Plant Permitting Renewal
The town is currently working with Hurt & Proffitt and the Virginia Department of Environmental Quality to renew our operating permit under the Virginia Pollutant Discharge Elimination System (VPDES). This renewal is required every five years and this is the first renewal since the town moved away from land application of biosolids and also the first since monitoring for PFAS is required.
The staff continues to take the steps required for permit renewal. I signed the renewal request packet and it was submitted to DEQ last week. As a reminder, the town’s current discharge permit expires May 3, 2026.
-
Wastewater Treatment Plant Permitting Renewal
The town is currently working with Hurt & Proffitt and the Virginia Department of Environmental Quality to renew our operating permit under the Virginia Pollutant Discharge Elimination System (VPDES). This renewal is required every five years and this is the first renewal since the town moved away from land application of biosolids and also the first since monitoring for PFAS is required.
The staff continues to take the steps required for permit renewal. As a reminder, the town’s current discharge permit expires May 3, 2026.
-
Wastewater Treatment Plant Permitting Renewal
The town is currently working with Hurt & Proffitt and the Virginia Department of Environmental Quality to renew our operating permit under the Virginia Pollutant Discharge Elimination System (VPDES). This renewal is required every five years and this is the first renewal since the town moved away from land application of biosolids and also the first since monitoring for PFAS is required.
The staff continues to take the steps required for permit renewal. Attached is our official notification letter from DEQ. the town’s current discharge permit expires May 3, 2026.
-
Wastewater Treatment Plant Permitting Renewal
The town is currently working with Hurt & Proffitt and the Virginia Department of Environmental Quality to renew our operating permit under the Virginia Pollutant Discharge Elimination System (VPDES). This renewal is required every five years and this is the first renewal since the town moved away from land application of biosolids and also the first since monitoring for PFAS is required.
The staff continues to take the steps required for permit renewal. A copy of the town’s agreement with Hurt & Proffitt to assist with this process is located in your agenda packet. As a reminder, the town’s current discharge permit expires May 3, 2026.
-
Wastewater Treatment Plant Permitting Renewal
The town is currently working with Hurt & Proffitt and the Virginia Department of Environmental Quality to renew our operating permit under the Virginia Pollutant Discharge Elimination System (VPDES). This renewal is required every five years and this is the first renewal since the town moved away from land application of biosolids and also the first since monitoring for PFAS is required.
The staff continues to take the steps required for permit renewal. Attached is our official notification letter from DEQ. the town’s current discharge permit expires May 3, 2026.
-
Wastewater Treatment Plant Permitting Renewal
The town is currently working with Hurt & Proffitt and the Virginia Department of Environmental Quality to renew our operating permit under the Virginia Pollutant Discharge Elimination System (VPDES). This renewal is required every five years and this is the first renewal since the town moved away from land application of biosolids and also the first since monitoring for PFAS is required.
Town staff met with Hurt & Proffitt staff last week for our “kick off” meeting. Work will continue to work towards our renewal deadline of Spring 2026.