City Manager Report December 8, 2025
Maple Street • We had a lengthy meeting this week to go over the plans for the Maple Street project and additional bid items, including Mary Street, water main gate valves for Water Street, and boardwalk concrete and seawall repairs. • F&V advised we are still on track to receive our EGLE permit and go out to bid in mid-December. We look forward to a bid opening in January/early February. • The start of construction is still planned for spring and will last into the fall. Mt. Baldhead Restroom Construction • Midwest Construction provided the following update: o Recently complete: Interior Paint Flooring o Next up: Electrical, plumbing and HVAC fixtures. Inspections to follow. Countertops and Accessory install Concrete sidewalk approach Complete Soffit/Fascia/Gutters
Page 11
Text of page 11
Project Workload • The Council set a big priority list for FY 25/26. The staff team is working on tackling many of the priorities, including some very large and exciting projects. We will talk more about the progress at your January strategic planning meeting, but wanted the Council to get a sense of what projects we are actively working on: Maple Street – Road, Watermain, Sidewalk, Sewer Repairs, Stormwater Mary Street – Resurfacing and Stormwater Seawall/Concrete Repairs Public Works Lot and Driveway Resurfacing Public Works Sewer Lateral Repairs Chain Ferry Arbors and Landings Holiday Lighting – Electrical and Expansion Sidewalk Replacements Hoffman and Wicks Part Resurfacing and Line Repainting Elizabeth Street Design Frontier Fiber Installation City Hall Elevator Repairs Asset Management and CIP Plans Sculpture Cleaning Dock Repairs Mt. Baldhead Restroom MT. Baldhead Revegetation SHNA Invasives, Evaluation and Signage New Truck and Snowplow Purchase Oval Beach Concessions RFP Oval Beach Roller Covers Invasive Species Inventory/Plan Deer Cull
Parking Improvements Blue Star Trail Fire Code Update Updated Water and Sewer Agreement Duneridge Litigation Logo and Branding Mt. Baldhead Upper Platform Warming Station Park Street Grant and Engineering Proposal AT&T Cellular Policy Updates Kalamazoo River Greenway Village Square Court Donation and Grant Records Scanning City Hall Interior Redesign Website Updates Online Payments Options Annual Audit Updated Master Plan Updated Sign Regulations Consolidation of Commercial Zoning Districts Auction Surplus Trucks and Equipment
Warming Stations • I talked with Lisa Mize this week. She is working on reviewing the feedback from Council, Parks and Public Works Committee, and survey. • Lisa will be at a future workshop to discuss the plans further. Strategic Planning for FY 26/27 • I have been digesting the Council’s recent feedback for a January strategic planning session. More to come at the next workshop meeting. Miscellaneous • Held one on one with Public Works Superintendent.
Page 12
Text of page 12
Held Department Head team meeting. Met with interim KLSWA Administrator. Met with Township representatives regarding sewer capacity. Attended Safe Routes to School meeting. Finalized water/sewer authority feedback and sent to consultant and committee members.
Page 13
Text of page 13
Treasurer Report
December 08, 2025
Tax Administration • • • •
Fielded resident inquiries related to mailing addresses, PREs, deferments, and partial payments. Researched returned or undeliverable mail and updated address records accordingly. Coordinated address and contact updates with the Assessor’s Office to ensure property records reflect current ownership information. Continued receiving summer tax payments and started receiving winter tax payments and preparing property tax disbursements to Allegan County, Saugatuck Public Schools, and OAISD. These distributions will continue on each payables through March 1. Finished winter tax preparation, printed, and mailed the tax bills. Identified a discrepancy in the chargeback distribution from Allegan County. The City had not received the full amount due; the County has been contacted, and the correction is in process.
Accounts Payable • • • •
Coordinated with vendors on payment processing and account updates. Received credits from Comcast for a variety of fees. Continuing to work with them on improved pricing. Followed up with Republic Services to ensure a service credit will be properly applied to the other account after a delayed cancellation. Processed regular payables, including the property tax disbursement batch.
Payroll & Benefits • •
Processed two payrolls. Coordinated DOT drug/alcohol testing setup for new DPW employees, ensuring they are enrolled in the required testing program prior to starting safety-sensitive duties.
Financial Management / Audit Preparation • •
Processed credit card payments for permits. Addressed follow-up requests from the auditor
Page 14
Text of page 14
Completed the October bank reconciliation. Began the process of updating the City’s bank signatories to reflect current personnel and ensure alignment with required financial controls.
Investments and Banking •
Shifted some more idle balances into MiCLASS to maximize interest returns.
Miscellaneous / Administrative •
Renewed the SAM.gov account. Continued coordinating quotes for the City Hall fire alarm and monitoring system upgrade. The initial vendor proposal is ready; I am currently awaiting confirmation from the Fire Department that the specifications meet all required standards before proceeding. Completed the seasonal shutdown of the Oval Beach credit card terminal and coordinated with the processor to ensure the account is placed in off-season status.
Page 15
Text of page 15
City Clerk Monthly Report Records Management • Submitted all 2025 ordinances to American Legal Publishing for codification. Meetings • Prepared agendas, packets, and minutes for the following: o City Council Workshop o Two City Council Regular Meetings o Historic District Commission Meeting o Planning Commission Meeting o Parks & Public Works Committee Meeting • Attended Department Head Meeting. • Participated in CVB 2026 Special Events discussion. • Administered oaths of office to Councilmembers. Special Events • Conducted safety meetings and prepared event recaps for: o Tree Lighting Ceremony o Christmas Parade o Veterans Day Event • Received, reviewed, and initiated processing for four 2026 special event applications. Administrative & General • Continued website updates and creation of new pages; completed review of all links for accuracy and accessibility. • Researched and ordered an exterior camera for the City Hall mail slot, required for election security. • Prepared and mailed holiday cards. • Sent 109 mailers. • Prepared, stuffed, and mailed tax notices. • Created and distributed 18 E-News blasts to the community. • Completed continuing education for election accreditation. • Managed front counter operations as the primary point of contact for
Page 16
Text of page 16
walk-ins and phone inquiries. City Hall staff received a total of 245 calls. City Hall Remodel: Received initial architectural renderings; meeting scheduled for review and discussion.
Page 17
Text of page 17
November Planning, Zoning, & Project Report Planning & Zoning • • • • • • • • • • • • • • • • • • •
Created voting location map for the Clerk’s office. Provided guidance on event liquor and tent permitting requirements. Responded to land split and conservation inquiry. Continuous coordination with City Engineer on active and proposed projects. Conducted STR compliance checks on new property transfers and galvanized service line updates. Documented recommended revisions to Planning Commission, Historic District Commission, and Zoning Board of Appeals Bylaws. Coordinated sign ordinance updates and public-facing guidance (digital + field postings). Advanced Historic District sign amendments and discussed updated proposal received by consultant. Prepared agendas, packets, and materials for Planning Commission, Zoning Board of Appeals, and Historic District Commission meetings. Continued Master Plan survey data analysis, demographics research, internal coordination, and mapping work. Updated invoice tracking and escrow logs; maintained financial records. Researched Fire Department request for 2024 IFC adoption; reviewed implications with staff. Further discussion with City Manager over memo sent. Conducted field inspections for code compliance and zoning verification. Engaged with residents regarding active projects, zoning inquiries, short term rentals, and enforcement matters. Maintained ongoing communication with legal counsel on enforcement strategy. Continued enforcement follow-ups and outreach on ongoing violations. Issued permits and processed planning/zoning casework as documented in case log. Participated in internal staff coordination meetings. Met with Fire Department staff to review standards and active cases. 1
Page 18
Text of page 18
Open Casework Items Associated with Granicus Short-Term Rental Hotline: 510 Butler
Special Land Use
PC approved with conditions. Need to pursue parcel combination.
102 Butler
Historic / Zoning
Rose Garden warming station. Plans in progress. Presented at PPW meeting and conducting survey.
700 N Maple
Enforcement
Correspondence between resident and legal is ongoing.
665 Spear
Enforcement
Concern raised of current condition of existing drainage system. Engineering to review. Meeting with resident scheduled.
150 Dunegrass
Zoning
120 Mary/510 Butler
Enforcement
125 Mason
Short Term Rental
Pending Fire Department inspection approval.
249 Culver #1
Short Term Rental
Pending Fire Department inspection approval.
249 Culver #2
Short Term Rental
Pending Fire Department inspection approval.
60 Griffith
Short Term Rental
Pending Fire Department inspection approval.
125 Elizabeth
Enforcement
Ongoing communication with resident and other applicable departments to come to an agreeable solution.
123 North
Short Term Rental
Pending Fire Department inspection approval.
249 Mason
Zoning
Planning Commission approved with conditions. Pending Fire Department approval.
555 Grand
Short Term Rental
Pending Fire Department inspection approval.
Single family residence proposed. Applicant working with Fire Department on access lane. Mature arborvitae planted as screening. Exceeds height limit for fencing. Met with owner to discuss remedy. Will assign a “date to be removed by” after further discussion.
Page 19
Text of page 19
125 Water
Short Term Rental
Pending Fire Department inspection approval.
201 Culver
Short Term Rental
Pending Fire Department inspection approval.
57-850-010-00
Zoning / ZBA
Single family residence with detached ADU. Pursuing variance at December ZBA meeting.
640 Water
PUD
Application submitted to be on the December Planning Commission meeting.
807 Lake #2
Short Term Rental
Pending Fire Department inspection approval.
546 Butler
Historic
Exterior street facing door change to be on the December Historic District Commission meeting.
510 Butler
Special Land Use
Pursuing Special Land Use approval to provide service of alcoholic beverages. Applicant working with staff.
250 Mason
Zoning
Application for a change of use to a Bed & Breakfast Establishment. Renovation of existing building.
254 Francis
Enforcement
Received complaint about renting a STR without a license. Violation letter sent to owner.
405 Park
Zoning
Applicant awaiting permit approval from EGLE.
Page 20
Text of page 20
Closed Casework 840 Lake
Short Term Rental
Renewal processed; Fire inspection failed then cleared; fees paid; license issued
Ottowa Area ISD
Right of Way
Fiber work reviewed; invoice sent; approved with conditions
879 Holland
Short Term Rental
Application complete; Fire approval secured; license issued
1045 Elizabeth
C of O
Inspection requested and approved
720 Park
Zoning
Deck application approved; no expansion
126 Park
Short Term Rental
License expired; non-renewable
842 Lake #1
Short Term Rental
License expired; owner advised on compliance; no current STR activity; future application expected
246 Culver
Right of Way
Temporary lighting permit issued; fees paid
408 Mason
Short Term Rental
Change of ownership; documentation updated; Fire approval; license issued
735 Park
Zoning / Connection
Water/sewer connection review in process for construction project
260 Brook
Enforcement
Operating STR without valid license; notification sent
142 Butler
Zoning / Historic
Site plan under review; engineering and fire cleared; conditions resolved; approved
433 Grand
Connection
Sewer replacement reviewed; materials received; fee paid; permit issued
810 Allegan
Enforcement
STR ownership change triggered enforcement; license revoked
290 Spear
Enforcement
Travel trailer violation processed; notices sent; follow-up confirmed temporary occupancy had been taking place; has been resolved
247 Grand
Zoning
Breezeway enclosure; footprint coverage addressed; engineering cleared; permit issued
Page 21
Text of page 21
515 Park
Short Term Rental
Ownership change; Fire approval; license issued
141 West
Zoning Inquiry
Provided process clarification on alley vacation and legal considerations
202 Butler
Right of Way
Water service replacement; invoice sent; fee paid; permit issued.
449 Water
Enforcement
ROW storage violation; items removed
160 N Maple
Zoning
Water service line replacement reviewed and approved.
610 Lake
Special Land Use
STR for ADU processed; public notice completed; approved at PC.
775 Manchester
Enforcement
Trash left out several days after pick up.
665 Spear
Enforcement
Trash complaint validated; confirmed resolved.
Page 22
Text of page 22
Department of Public Works Below is a summary of notable activities carried out by the Department of Public Works since the last summary provided to City Council at the November 10th regular meeting. Brush and Leaf Collection: October through December is considered the peak for fall cleanup by Public Works staff. Several days and hundreds of dump trucks full of material have been hauled out of the City to serve property owners. The final collection was just before Thanksgiving which was great timing this year because snow arrived shortly after. This required Public Works staff to quickly outfit equipment for snow and ice control services. Christmas Decorations: In between brush and leaf collection services, Public Works staff worked to install Christmas decorations at Coghlin Park, City Hall, Jones Park, Rose Garden, Village Square, Wicks Park, town entrances, and on utility poles. Although Public Works takes an active role in coordinating the work, the streetscaping lights that are wrapped around trees are installed by Chips Groundcover. DPW will routinely monitor outages and work to keep the lights on as much as possible. Project Updates: Holiday Lights – All lights are installed and we’re waiting on Consumer’s Energy to finish electrical work on 2 poles that were missed during the original round of work. Consumer’s Energy states that the work will be completed by the end of the week of 12/1. Chain Ferry Arbors – Diversified Welding and Fabrication is targeting the third week of December for installation. Sidewalk Replacements – 15/21 are completed. Will finish the remaining spring of 2026. City Hall Elevator – Work is underway. Seeking an update from McNally Elevator. Pavement Markings – ACE Parking Lot Striping has completed the work. Sculpture Cleaning – Complete. Mt. Baldhead Restrooms – Construction underway and the project is on schedule.
Special Event Assistance: • Veteran’s Day • Turkey Trot Run • Whootville Christmas Parade Meetings: • 11/10/2025 – DPW Weekly Goals Meeting • 11/12/2025 – Second Interview – Equipment Operator/Maintenance Worker/Oval Beach Manager • 11/12/2025 – Department Head Team Meeting • 11/13/2025 – Elizabeth Street Walkthrough/Design Meeting • 11/14/2025 – DPW Weekly Goals Follow Up Meeting • 11/17/2025 – DPW Weekly Goals Meeting
Page 23
Text of page 23
11/20/2025 – Special Event Safety Meeting – Tree Lighting/Whootville Christmas Parade 11/21/2025 – DPW Weekly Goals Follow Up Meeting 11/24/2025 – DPW Weekly Goals Meeting 11/25/2025 – Parks & Public Works Committee Meeting 11/26/2025 – Department Head Team Meeting 11/26/2025 – DPW Weekly Goals Follow Up Meeting 12/01/2025 – DPW Weekly Goals Meeting 12/02/2025 – One-on-One Meeting – City Manager & Public Works Superintendent 12/02/2025 – White Alley Vacancy Meeting 12/04/2025 – Maple Street Plan Review 12/05/2025 – DPW Weekly Goals Follow Up Meeting
Page 24
Text of page 24
Saugatuck November 2025 Total traffic stops – 37 School contacts - 23
Call Date/Time
Incident Type
=================== =================== 11/30/2025 21:48:02
General Assist
11/29/2025 22:18:42
General Assist
11/28/2025 21:50:34
General Assist
11/28/2025 07:57:03
CARDIAC/RESP ARREST
11/28/2025 01:26:53
General Assist
11/27/2025 20:02:58
Misc
11/27/2025 09:47:10
General Assist
11/27/2025 09:31:45
Inspections
11/27/2025 09:29:03
Inspections
11/26/2025 23:39:43
Check Welfare
11/26/2025 23:22:48
General Assist
11/26/2025 17:39:44
Motorist Assist
11/26/2025 16:58:02
Alarm
11/26/2025 09:07:07
Alarm
11/26/2025 01:17:34
Accident All Other
11/26/2025 00:15:20
General Assist
11/25/2025 16:55:02
Check Welfare
11/24/2025 22:08:34
General Assist
11/24/2025 09:56:46
Inspections
11/23/2025 23:18:48
General Assist
11/23/2025 21:26:41
Larceny
11/23/2025 02:15:49
Inspections
11/22/2025 23:36:56
General Assist
11/22/2025 15:29:32
General Assist
11/21/2025 23:27:30
General Assist
11/21/2025 08:52:07
Inspections
11/21/2025 08:48:16
Inspections
11/20/2025 22:41:27
General Assist
11/20/2025 18:44:40
Fraud
11/20/2025 13:30:24
Parking Violation
11/20/2025 13:20:18
Parking Violation
11/19/2025 21:54:34
General Assist
11/18/2025 22:36:49
General Assist
11/17/2025 22:32:20
General Assist
11/17/2025 15:04:04
Assault
11/17/2025 14:30:42
Check Welfare
11/17/2025 10:17:42
Inspections
11/17/2025 10:14:10
Inspections
11/16/2025 22:28:22
General Assist
11/15/2025 22:26:13
General Assist
11/15/2025 18:37:59
No Ops
11/15/2025 17:14:07
Alarm
11/14/2025 23:13:14
General Assist
11/14/2025 14:42:22
Parking Violation
11/14/2025 09:08:34
Inspections
11/14/2025 09:00:35
Inspections
11/14/2025 02:26:57
Inspections
11/14/2025 02:21:41
Inspections
11/14/2025 02:19:02
General Assist
11/13/2025 17:01:06
Parking Violation
Page 25
Text of page 25
11/12/2025 23:02:00
General Assist
11/01/2025 15:03:10
FALLS
11/12/2025 17:41:34
Traffic Offense
11/01/2025 00:33:31
Accident All Other
11/12/2025 01:23:49
General Assist
11/11/2025 13:33:17
Alarm
11/11/2025 13:16:15
Fire Alarm
11/11/2025 08:49:18
General Assist
11/10/2025 21:41:12
General Assist
11/10/2025 12:03:19
SICK PERSON
11/09/2025 23:09:07
General Assist
11/09/2025 19:10:07
Alarm
11/09/2025 02:50:21
General Assist
11/08/2025 15:11:32
A911
11/08/2025 02:27:21
Inspections
11/08/2025 02:21:00
Inspections
11/07/2025 22:37:43
Domestic Assault
11/07/2025 22:19:10
General Assist
11/07/2025 19:57:46
General Assist
11/06/2025 21:52:37
General Assist
11/06/2025 12:53:17
Fire Alarm
11/06/2025 00:06:21
General Assist
11/05/2025 11:46:57
Inspections
11/05/2025 11:40:04
Inspections
11/04/2025 18:41:51
A911
11/03/2025 22:14:37
General Assist
11/03/2025 10:19:54
Inspections
11/03/2025 10:16:01
Inspections
11/02/2025 21:59:08
Disorderly Conduct
11/02/2025 21:55:00
General Assist
11/01/2025 20:42:41
Trespassing
Page 26
Text of page 26
City of Saugatuck Status Report of Engineering Activities December 4, 2025 General Consultation •
Village Square Court Renovation: Received final scoring – revisions increased us from 140 to 185 points, which may be in the fundable range. Results are expected from DNR at any time.
Developed a proposal for inspection of larger culvert crossings and storm sewer outfalls. This work could be completed in phases and areas of concern could be prioritized.
Pavement Markings: 2025 work is complete. 2026 work will take place in the spring. Current contract is 2025-2027.
Assisting with review of water and sewer agreements as needed.
2025 Asphalt Improvements: Project is complete.
Assisting with site plan reviews and construction observation for new development and other projects as needed.
EGLE Technical, Managerial and Financial (TMF) Project • •
The project is complete, final documents have been submitted to EGLE and notices have been sent to customers. Assisting staff with answering customer questions. Will be working with City staff on a plan to eliminate remaining unknowns and replace lead/galvanized services by the federal and state deadlines (11/1/2037 and 1/1/2041, respectively).
Mt. Baldhead Projects • •
AT&T Project Assistance o Providing assistance on an as-needed basis. Restroom Building Replacement o Construction is approaching completion. The building envelope is complete, except for doors. Interior work is anticipated to be completed in December. Final site restoration will be completed in spring 2026. Observation Platform Replacement o Attended several meetings with area stakeholders and cultural resources specialists to help guide the design. o Received report of findings on cultural resources and anticipate meeting again with stakeholders soon. o Timeframe for design and construction will depend on the direction for design based on stakeholder input.
Sea Wall and Concrete Repairs • •
The bid opening was held on April 30, however none were received. The DPW will be obtaining quotes for patching stairs at Hoffman & Griffith. The remaining areas are being incorporated as additional work within the Maple Street contract.
Page 27
Text of page 27
Maple Street Improvements • • •
EGLE permitting is in the final review phase. Incorporated sea wall repairs, resurfacing Mary Street (Water Street to Butler Street) and new valves on Water Street into the bid documents as separate items of work (outside the Maple Street budget). Depending on timing for permits and final design, we anticipate issuing the project for bids in yet in December 2025 with construction during the 2026 construction season (approximately April to November).
Park Street Improvements – Study Phase •
Park Street between Campbell Road and Mt. Baldhead has no specific non-motorized facility and a number of unique challenges and right-of-way encroachments. The asphalt pavement is deteriorating. A number of development projects have recently been completed or are ongoing along the corridor. A planning phase proposal has been developed to build on prior study work and develop a scope, concept and cost estimate for improvement of the corridor. We are awaiting results of our application to EGLE’s Michigan Coastal Management Program, which was submitted on December 20, 2024 followed by a council resolution on December 23. If funded, the grant would cover up to 50% of the planning cost and an updated proposal will be prepared to align with the funding. EGLE has reached out several times with follow-up questions/clarifications on the application.
City Hall Interior Renovations •
Prepared a conceptual floor plan that incorporates findings from the needs evaluation for staff comment.
Elizabeth Street Improvements • •
Planning phase proposal was reviewed at the December 3 workshop for Council consideration at the December 8 meeting. Projected schedule is planning work in early 2026, design in mid-2026, bidding in late 2026 and construction in 2027.