City Manager Report December 8, 2025

Maple Street • We had a lengthy meeting this week to go over the plans for the Maple Street project and additional bid items, including Mary Street, water main gate valves for Water Street, and boardwalk concrete and seawall repairs. • F&V advised we are still on track to receive our EGLE permit and go out to bid in mid-December. We look forward to a bid opening in January/early February. • The start of construction is still planned for spring and will last into the fall. Mt. Baldhead Restroom Construction • Midwest Construction provided the following update: o Recently complete:  Interior Paint  Flooring o Next up:  Electrical, plumbing and HVAC fixtures. Inspections to follow.  Countertops and Accessory install  Concrete sidewalk approach  Complete Soffit/Fascia/Gutters

Page 11

Page 11 of the packet; its text follows
Text of page 11

Project Workload • The Council set a big priority list for FY 25/26. The staff team is working on tackling many of the priorities, including some very large and exciting projects. We will talk more about the progress at your January strategic planning meeting, but wanted the Council to get a sense of what projects we are actively working on: Maple Street – Road, Watermain, Sidewalk, Sewer Repairs, Stormwater Mary Street – Resurfacing and Stormwater Seawall/Concrete Repairs Public Works Lot and Driveway Resurfacing Public Works Sewer Lateral Repairs Chain Ferry Arbors and Landings Holiday Lighting – Electrical and Expansion Sidewalk Replacements Hoffman and Wicks Part Resurfacing and Line Repainting Elizabeth Street Design Frontier Fiber Installation City Hall Elevator Repairs Asset Management and CIP Plans Sculpture Cleaning Dock Repairs Mt. Baldhead Restroom MT. Baldhead Revegetation SHNA Invasives, Evaluation and Signage New Truck and Snowplow Purchase Oval Beach Concessions RFP Oval Beach Roller Covers Invasive Species Inventory/Plan Deer Cull

Parking Improvements Blue Star Trail Fire Code Update Updated Water and Sewer Agreement Duneridge Litigation Logo and Branding Mt. Baldhead Upper Platform Warming Station Park Street Grant and Engineering Proposal AT&T Cellular Policy Updates Kalamazoo River Greenway Village Square Court Donation and Grant Records Scanning City Hall Interior Redesign Website Updates Online Payments Options Annual Audit Updated Master Plan Updated Sign Regulations Consolidation of Commercial Zoning Districts Auction Surplus Trucks and Equipment

Warming Stations • I talked with Lisa Mize this week. She is working on reviewing the feedback from Council, Parks and Public Works Committee, and survey. • Lisa will be at a future workshop to discuss the plans further. Strategic Planning for FY 26/27 • I have been digesting the Council’s recent feedback for a January strategic planning session. More to come at the next workshop meeting. Miscellaneous • Held one on one with Public Works Superintendent.

Page 12

Page 12 of the packet; its text follows
Text of page 12

Held Department Head team meeting. Met with interim KLSWA Administrator. Met with Township representatives regarding sewer capacity. Attended Safe Routes to School meeting. Finalized water/sewer authority feedback and sent to consultant and committee members.

Page 13

Page 13 of the packet; its text follows
Text of page 13

Treasurer Report

December 08, 2025

Tax Administration • • • •

Fielded resident inquiries related to mailing addresses, PREs, deferments, and partial payments. Researched returned or undeliverable mail and updated address records accordingly. Coordinated address and contact updates with the Assessor’s Office to ensure property records reflect current ownership information. Continued receiving summer tax payments and started receiving winter tax payments and preparing property tax disbursements to Allegan County, Saugatuck Public Schools, and OAISD. These distributions will continue on each payables through March 1. Finished winter tax preparation, printed, and mailed the tax bills. Identified a discrepancy in the chargeback distribution from Allegan County. The City had not received the full amount due; the County has been contacted, and the correction is in process.

Accounts Payable • • • •

Coordinated with vendors on payment processing and account updates. Received credits from Comcast for a variety of fees. Continuing to work with them on improved pricing. Followed up with Republic Services to ensure a service credit will be properly applied to the other account after a delayed cancellation. Processed regular payables, including the property tax disbursement batch.

Payroll & Benefits • •

Processed two payrolls. Coordinated DOT drug/alcohol testing setup for new DPW employees, ensuring they are enrolled in the required testing program prior to starting safety-sensitive duties.

Financial Management / Audit Preparation • •

Processed credit card payments for permits. Addressed follow-up requests from the auditor

Page 14

Page 14 of the packet; its text follows
Text of page 14

Completed the October bank reconciliation. Began the process of updating the City’s bank signatories to reflect current personnel and ensure alignment with required financial controls.

Investments and Banking •

Shifted some more idle balances into MiCLASS to maximize interest returns.

Miscellaneous / Administrative •

Renewed the SAM.gov account. Continued coordinating quotes for the City Hall fire alarm and monitoring system upgrade. The initial vendor proposal is ready; I am currently awaiting confirmation from the Fire Department that the specifications meet all required standards before proceeding. Completed the seasonal shutdown of the Oval Beach credit card terminal and coordinated with the processor to ensure the account is placed in off-season status.

Page 15

Page 15 of the packet; its text follows
Text of page 15

City Clerk Monthly Report Records Management • Submitted all 2025 ordinances to American Legal Publishing for codification. Meetings • Prepared agendas, packets, and minutes for the following: o City Council Workshop o Two City Council Regular Meetings o Historic District Commission Meeting o Planning Commission Meeting o Parks & Public Works Committee Meeting • Attended Department Head Meeting. • Participated in CVB 2026 Special Events discussion. • Administered oaths of office to Councilmembers. Special Events • Conducted safety meetings and prepared event recaps for: o Tree Lighting Ceremony o Christmas Parade o Veterans Day Event • Received, reviewed, and initiated processing for four 2026 special event applications. Administrative & General • Continued website updates and creation of new pages; completed review of all links for accuracy and accessibility. • Researched and ordered an exterior camera for the City Hall mail slot, required for election security. • Prepared and mailed holiday cards. • Sent 109 mailers. • Prepared, stuffed, and mailed tax notices. • Created and distributed 18 E-News blasts to the community. • Completed continuing education for election accreditation. • Managed front counter operations as the primary point of contact for

Page 16

Page 16 of the packet; its text follows
Text of page 16

walk-ins and phone inquiries. City Hall staff received a total of 245 calls. City Hall Remodel: Received initial architectural renderings; meeting scheduled for review and discussion.

Page 17

Page 17 of the packet; its text follows
Text of page 17

November Planning, Zoning, & Project Report Planning & Zoning • • • • • • • • • • • • • • • • • • •

Created voting location map for the Clerk’s office. Provided guidance on event liquor and tent permitting requirements. Responded to land split and conservation inquiry. Continuous coordination with City Engineer on active and proposed projects. Conducted STR compliance checks on new property transfers and galvanized service line updates. Documented recommended revisions to Planning Commission, Historic District Commission, and Zoning Board of Appeals Bylaws. Coordinated sign ordinance updates and public-facing guidance (digital + field postings). Advanced Historic District sign amendments and discussed updated proposal received by consultant. Prepared agendas, packets, and materials for Planning Commission, Zoning Board of Appeals, and Historic District Commission meetings. Continued Master Plan survey data analysis, demographics research, internal coordination, and mapping work. Updated invoice tracking and escrow logs; maintained financial records. Researched Fire Department request for 2024 IFC adoption; reviewed implications with staff. Further discussion with City Manager over memo sent. Conducted field inspections for code compliance and zoning verification. Engaged with residents regarding active projects, zoning inquiries, short term rentals, and enforcement matters. Maintained ongoing communication with legal counsel on enforcement strategy. Continued enforcement follow-ups and outreach on ongoing violations. Issued permits and processed planning/zoning casework as documented in case log. Participated in internal staff coordination meetings. Met with Fire Department staff to review standards and active cases. 1

Page 18

Page 18 of the packet; its text follows
Text of page 18

Open Casework Items Associated with Granicus Short-Term Rental Hotline: 510 Butler

Special Land Use

PC approved with conditions. Need to pursue parcel combination.

102 Butler

Historic / Zoning

Rose Garden warming station. Plans in progress. Presented at PPW meeting and conducting survey.

700 N Maple

Enforcement

Correspondence between resident and legal is ongoing.

665 Spear

Enforcement

Concern raised of current condition of existing drainage system. Engineering to review. Meeting with resident scheduled.

150 Dunegrass

Zoning

120 Mary/510 Butler

Enforcement

125 Mason

Short Term Rental

Pending Fire Department inspection approval.

249 Culver #1

Short Term Rental

Pending Fire Department inspection approval.

249 Culver #2

Short Term Rental

Pending Fire Department inspection approval.

60 Griffith

Short Term Rental

Pending Fire Department inspection approval.

125 Elizabeth

Enforcement

Ongoing communication with resident and other applicable departments to come to an agreeable solution.

123 North

Short Term Rental

Pending Fire Department inspection approval.

249 Mason

Zoning

Planning Commission approved with conditions. Pending Fire Department approval.

555 Grand

Short Term Rental

Pending Fire Department inspection approval.

Single family residence proposed. Applicant working with Fire Department on access lane. Mature arborvitae planted as screening. Exceeds height limit for fencing. Met with owner to discuss remedy. Will assign a “date to be removed by” after further discussion.

Page 19

Page 19 of the packet; its text follows
Text of page 19

125 Water

Short Term Rental

Pending Fire Department inspection approval.

201 Culver

Short Term Rental

Pending Fire Department inspection approval.

57-850-010-00

Zoning / ZBA

Single family residence with detached ADU. Pursuing variance at December ZBA meeting.

640 Water

PUD

Application submitted to be on the December Planning Commission meeting.

807 Lake #2

Short Term Rental

Pending Fire Department inspection approval.

546 Butler

Historic

Exterior street facing door change to be on the December Historic District Commission meeting.

510 Butler

Special Land Use

Pursuing Special Land Use approval to provide service of alcoholic beverages. Applicant working with staff.

250 Mason

Zoning

Application for a change of use to a Bed & Breakfast Establishment. Renovation of existing building.

254 Francis

Enforcement

Received complaint about renting a STR without a license. Violation letter sent to owner.

405 Park

Zoning

Applicant awaiting permit approval from EGLE.

Page 20

Page 20 of the packet; its text follows
Text of page 20

Closed Casework 840 Lake

Short Term Rental

Renewal processed; Fire inspection failed then cleared; fees paid; license issued

Ottowa Area ISD

Right of Way

Fiber work reviewed; invoice sent; approved with conditions

879 Holland

Short Term Rental

Application complete; Fire approval secured; license issued

1045 Elizabeth

C of O

Inspection requested and approved

720 Park

Zoning

Deck application approved; no expansion

126 Park

Short Term Rental

License expired; non-renewable

842 Lake #1

Short Term Rental

License expired; owner advised on compliance; no current STR activity; future application expected

246 Culver

Right of Way

Temporary lighting permit issued; fees paid

408 Mason

Short Term Rental

Change of ownership; documentation updated; Fire approval; license issued

735 Park

Zoning / Connection

Water/sewer connection review in process for construction project

260 Brook

Enforcement

Operating STR without valid license; notification sent

142 Butler

Zoning / Historic

Site plan under review; engineering and fire cleared; conditions resolved; approved

433 Grand

Connection

Sewer replacement reviewed; materials received; fee paid; permit issued

810 Allegan

Enforcement

STR ownership change triggered enforcement; license revoked

290 Spear

Enforcement

Travel trailer violation processed; notices sent; follow-up confirmed temporary occupancy had been taking place; has been resolved

247 Grand

Zoning

Breezeway enclosure; footprint coverage addressed; engineering cleared; permit issued

Page 21

Page 21 of the packet; its text follows
Text of page 21

515 Park

Short Term Rental

Ownership change; Fire approval; license issued

141 West

Zoning Inquiry

Provided process clarification on alley vacation and legal considerations

202 Butler

Right of Way

Water service replacement; invoice sent; fee paid; permit issued.

449 Water

Enforcement

ROW storage violation; items removed

160 N Maple

Zoning

Water service line replacement reviewed and approved.

610 Lake

Special Land Use

STR for ADU processed; public notice completed; approved at PC.

775 Manchester

Enforcement

Trash left out several days after pick up.

665 Spear

Enforcement

Trash complaint validated; confirmed resolved.

Page 22

Page 22 of the packet; its text follows
Text of page 22

Department of Public Works Below is a summary of notable activities carried out by the Department of Public Works since the last summary provided to City Council at the November 10th regular meeting. Brush and Leaf Collection: October through December is considered the peak for fall cleanup by Public Works staff. Several days and hundreds of dump trucks full of material have been hauled out of the City to serve property owners. The final collection was just before Thanksgiving which was great timing this year because snow arrived shortly after. This required Public Works staff to quickly outfit equipment for snow and ice control services. Christmas Decorations: In between brush and leaf collection services, Public Works staff worked to install Christmas decorations at Coghlin Park, City Hall, Jones Park, Rose Garden, Village Square, Wicks Park, town entrances, and on utility poles. Although Public Works takes an active role in coordinating the work, the streetscaping lights that are wrapped around trees are installed by Chips Groundcover. DPW will routinely monitor outages and work to keep the lights on as much as possible. Project Updates: Holiday Lights – All lights are installed and we’re waiting on Consumer’s Energy to finish electrical work on 2 poles that were missed during the original round of work. Consumer’s Energy states that the work will be completed by the end of the week of 12/1. Chain Ferry Arbors – Diversified Welding and Fabrication is targeting the third week of December for installation. Sidewalk Replacements – 15/21 are completed. Will finish the remaining spring of 2026. City Hall Elevator – Work is underway. Seeking an update from McNally Elevator. Pavement Markings – ACE Parking Lot Striping has completed the work. Sculpture Cleaning – Complete. Mt. Baldhead Restrooms – Construction underway and the project is on schedule.

Special Event Assistance: • Veteran’s Day • Turkey Trot Run • Whootville Christmas Parade Meetings: • 11/10/2025 – DPW Weekly Goals Meeting • 11/12/2025 – Second Interview – Equipment Operator/Maintenance Worker/Oval Beach Manager • 11/12/2025 – Department Head Team Meeting • 11/13/2025 – Elizabeth Street Walkthrough/Design Meeting • 11/14/2025 – DPW Weekly Goals Follow Up Meeting • 11/17/2025 – DPW Weekly Goals Meeting

Page 23

Page 23 of the packet; its text follows
Text of page 23

11/20/2025 – Special Event Safety Meeting – Tree Lighting/Whootville Christmas Parade 11/21/2025 – DPW Weekly Goals Follow Up Meeting 11/24/2025 – DPW Weekly Goals Meeting 11/25/2025 – Parks & Public Works Committee Meeting 11/26/2025 – Department Head Team Meeting 11/26/2025 – DPW Weekly Goals Follow Up Meeting 12/01/2025 – DPW Weekly Goals Meeting 12/02/2025 – One-on-One Meeting – City Manager & Public Works Superintendent 12/02/2025 – White Alley Vacancy Meeting 12/04/2025 – Maple Street Plan Review 12/05/2025 – DPW Weekly Goals Follow Up Meeting

Page 24

Page 24 of the packet; its text follows
Text of page 24

Saugatuck November 2025 Total traffic stops – 37 School contacts - 23

Call Date/Time

Incident Type

=================== =================== 11/30/2025 21:48:02

General Assist

11/29/2025 22:18:42

General Assist

11/28/2025 21:50:34

General Assist

11/28/2025 07:57:03

CARDIAC/RESP ARREST

11/28/2025 01:26:53

General Assist

11/27/2025 20:02:58

Misc

11/27/2025 09:47:10

General Assist

11/27/2025 09:31:45

Inspections

11/27/2025 09:29:03

Inspections

11/26/2025 23:39:43

Check Welfare

11/26/2025 23:22:48

General Assist

11/26/2025 17:39:44

Motorist Assist

11/26/2025 16:58:02

Alarm

11/26/2025 09:07:07

Alarm

11/26/2025 01:17:34

Accident All Other

11/26/2025 00:15:20

General Assist

11/25/2025 16:55:02

Check Welfare

11/24/2025 22:08:34

General Assist

11/24/2025 09:56:46

Inspections

11/23/2025 23:18:48

General Assist

11/23/2025 21:26:41

Larceny

11/23/2025 02:15:49

Inspections

11/22/2025 23:36:56

General Assist

11/22/2025 15:29:32

General Assist

11/21/2025 23:27:30

General Assist

11/21/2025 08:52:07

Inspections

11/21/2025 08:48:16

Inspections

11/20/2025 22:41:27

General Assist

11/20/2025 18:44:40

Fraud

11/20/2025 13:30:24

Parking Violation

11/20/2025 13:20:18

Parking Violation

11/19/2025 21:54:34

General Assist

11/18/2025 22:36:49

General Assist

11/17/2025 22:32:20

General Assist

11/17/2025 15:04:04

Assault

11/17/2025 14:30:42

Check Welfare

11/17/2025 10:17:42

Inspections

11/17/2025 10:14:10

Inspections

11/16/2025 22:28:22

General Assist

11/15/2025 22:26:13

General Assist

11/15/2025 18:37:59

No Ops

11/15/2025 17:14:07

Alarm

11/14/2025 23:13:14

General Assist

11/14/2025 14:42:22

Parking Violation

11/14/2025 09:08:34

Inspections

11/14/2025 09:00:35

Inspections

11/14/2025 02:26:57

Inspections

11/14/2025 02:21:41

Inspections

11/14/2025 02:19:02

General Assist

11/13/2025 17:01:06

Parking Violation

Page 25

Page 25 of the packet; its text follows
Text of page 25

11/12/2025 23:02:00

General Assist

11/01/2025 15:03:10

FALLS

11/12/2025 17:41:34

Traffic Offense

11/01/2025 00:33:31

Accident All Other

11/12/2025 01:23:49

General Assist

11/11/2025 13:33:17

Alarm

11/11/2025 13:16:15

Fire Alarm

11/11/2025 08:49:18

General Assist

11/10/2025 21:41:12

General Assist

11/10/2025 12:03:19

SICK PERSON

11/09/2025 23:09:07

General Assist

11/09/2025 19:10:07

Alarm

11/09/2025 02:50:21

General Assist

11/08/2025 15:11:32

A911

11/08/2025 02:27:21

Inspections

11/08/2025 02:21:00

Inspections

11/07/2025 22:37:43

Domestic Assault

11/07/2025 22:19:10

General Assist

11/07/2025 19:57:46

General Assist

11/06/2025 21:52:37

General Assist

11/06/2025 12:53:17

Fire Alarm

11/06/2025 00:06:21

General Assist

11/05/2025 11:46:57

Inspections

11/05/2025 11:40:04

Inspections

11/04/2025 18:41:51

A911

11/03/2025 22:14:37

General Assist

11/03/2025 10:19:54

Inspections

11/03/2025 10:16:01

Inspections

11/02/2025 21:59:08

Disorderly Conduct

11/02/2025 21:55:00

General Assist

11/01/2025 20:42:41

Trespassing

Page 26

Page 26 of the packet; its text follows
Text of page 26

City of Saugatuck Status Report of Engineering Activities December 4, 2025 General Consultation •

Village Square Court Renovation: Received final scoring – revisions increased us from 140 to 185 points, which may be in the fundable range. Results are expected from DNR at any time.

Developed a proposal for inspection of larger culvert crossings and storm sewer outfalls. This work could be completed in phases and areas of concern could be prioritized.

Pavement Markings: 2025 work is complete. 2026 work will take place in the spring. Current contract is 2025-2027.

Assisting with review of water and sewer agreements as needed.

2025 Asphalt Improvements: Project is complete.

Assisting with site plan reviews and construction observation for new development and other projects as needed.

EGLE Technical, Managerial and Financial (TMF) Project • •

The project is complete, final documents have been submitted to EGLE and notices have been sent to customers. Assisting staff with answering customer questions. Will be working with City staff on a plan to eliminate remaining unknowns and replace lead/galvanized services by the federal and state deadlines (11/1/2037 and 1/1/2041, respectively).

Mt. Baldhead Projects • •

AT&T Project Assistance o Providing assistance on an as-needed basis. Restroom Building Replacement o Construction is approaching completion. The building envelope is complete, except for doors. Interior work is anticipated to be completed in December. Final site restoration will be completed in spring 2026. Observation Platform Replacement o Attended several meetings with area stakeholders and cultural resources specialists to help guide the design. o Received report of findings on cultural resources and anticipate meeting again with stakeholders soon. o Timeframe for design and construction will depend on the direction for design based on stakeholder input.

Sea Wall and Concrete Repairs • •

The bid opening was held on April 30, however none were received. The DPW will be obtaining quotes for patching stairs at Hoffman & Griffith. The remaining areas are being incorporated as additional work within the Maple Street contract.

Page 27

Page 27 of the packet; its text follows
Text of page 27

Maple Street Improvements • • •

EGLE permitting is in the final review phase. Incorporated sea wall repairs, resurfacing Mary Street (Water Street to Butler Street) and new valves on Water Street into the bid documents as separate items of work (outside the Maple Street budget). Depending on timing for permits and final design, we anticipate issuing the project for bids in yet in December 2025 with construction during the 2026 construction season (approximately April to November).

Park Street Improvements – Study Phase •

Park Street between Campbell Road and Mt. Baldhead has no specific non-motorized facility and a number of unique challenges and right-of-way encroachments. The asphalt pavement is deteriorating. A number of development projects have recently been completed or are ongoing along the corridor. A planning phase proposal has been developed to build on prior study work and develop a scope, concept and cost estimate for improvement of the corridor. We are awaiting results of our application to EGLE’s Michigan Coastal Management Program, which was submitted on December 20, 2024 followed by a council resolution on December 23. If funded, the grant would cover up to 50% of the planning cost and an updated proposal will be prepared to align with the funding. EGLE has reached out several times with follow-up questions/clarifications on the application.

City Hall Interior Renovations •

Prepared a conceptual floor plan that incorporates findings from the needs evaluation for staff comment.

Elizabeth Street Improvements • •

Planning phase proposal was reviewed at the December 3 workshop for Council consideration at the December 8 meeting. Projected schedule is planning work in early 2026, design in mid-2026, bidding in late 2026 and construction in 2027.